REFERENCE LIST |
Power (kW) |
Contract date |
Entering upon
working |
|
1 |
Customer |
Cartiere Miliani
Fabriano S.p.A. (AN) |
|
|
|
|
|
Object: |
Revamping
of S. Vittore plant:
Restructuring impellers and distributors of tree 340 kW Francis turbines,
replace of the generators, M.V. and L.V. switchboards and complete automation
of the plant. |
945 |
dic-86 |
ott-87 |
|
2 |
Customer |
Cartiere Miliani
Fabriano S.p.A. (AN) |
|
|
|
|
|
Object: |
Revamping
of Pianicella plant:
Restructuring impellers and distributors of two 1000 kW Francis
turbines, replace of the generators,
M.V. and L.V. switchboards and complete automation of the plant. |
2.000 |
dic-86 |
feb-88 |
|
3 |
Customer |
Nerawatt s.r.l. (MC) |
|
|
|
|
|
Object: |
Realization
of S. Antonio plant:
Supply and mounting of two hydroelectric units with 200 kW Francis
turbines, M.V. and L.V. switchboards
and complete automation of the plant. |
400 |
dic-88 |
dic-89 |
|
4 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of Rovetino plant on Sibillini Aqueduct:
Supply and mounting of two hydroelectric units with 315 kW Francis turbines
completed with rapid automatic by-pass system, M.V. and L.V. switchboards and complete
automation of the plant. |
630 |
set-87 |
gen-89 |
|
5 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of Ferriera plant on Sibillini Aqueduct:
Supply and mounting of two hydroelectric units with 200 kW Francis turbines
completed with rapid automatic by-pass system, M.V. and L.V. switchboards and complete
automation of the plant. |
400 |
set-87 |
ago-88 |
|
6 |
Customer |
Nerawatt s.r.l. (MC) |
|
|
|
|
|
Object: |
Realization
of S. Placido plant:
Supply and mounting of two hydroelectric units with 700 kW Francis
turbines, M.V. and L.V. switchboards
and complete automation of the plant. |
1.400 |
dic-88 |
nov-89 |
|
7 |
Customer |
Nerawatt s.r.l. (MC) |
|
|
|
|
|
Object: |
Realization
of S. Angelo plant:
Supply and mounting of one hydroelectric unit with 315 kW Francis
turbine, M.V. and L.V. switchboards
and complete automation of the plant. |
315 |
dic-88 |
feb-90 |
|
8 |
Customer |
Nerawatt s.r.l. (MC) |
|
|
|
|
|
Object: |
Realization
of S. Simone plant:
Supply and mounting of one hydroelectric unit with 650 kW Francis
turbines, M.V. and L.V. switchboards
and complete automation of the plant. |
650 |
dic-88 |
feb-90 |
|
9 |
Customer |
Comune di Villa Santa
Maria (CH) |
|
|
|
|
|
Object: |
Realization
of Castracane plant:
Supply and mounting of two hydroelectric units with 132 kW Francis
turbines, M.V. and L.V. switchboards
and complete automation of the plant. |
264 |
dic-89 |
mar-91 |
|
10 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of Faiano plant on PescaraAqueduct:
Supply and mounting of two hydroelectric units with 200 kW Francis turbines completed with
rapid automatic by-pass system, M.V.
and L.V. switchboards and complete automation of the plant. |
400 |
ott-89 |
feb-91 |
|
11 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of SS. Annunziata plant on Pescara Aqueduct:
Supply and mounting of one hydroelectric unit with 75 kW Francis turbines
completed with rapid automatic by- pass system, L.V. switchboards and complete automation
of the plant. |
75 |
ott-89 |
lug-90 |
|
12 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of Polesio plant on Pescara Aqueduct:
Supply and mounting of one hydroelectric unit with 315 kW Francis turbines
completed with rapid automatic by- pass system, M.V. and L.V. switchboards and complete
automation of the plant. |
315 |
ott-89 |
gen-91 |
|
13 |
Customer |
Comune di Borgo
Velino (RI) |
|
|
|
|
|
Object: |
Realization
of Fontanelle plant:
Supply and mounting of one hydroelectric unit with 30 kW Francis turbines,
L.V. switchboards and complete automation of the plant. |
30 |
ott-91 |
gen-93 |
|
14 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of Villa S. Antonio plant:
Supply and mounting of one hydroelectric unit with 475 kW Kaplan turbine
double regolation, 6000 l/sec., 9,5 m., automatic grille scraper, M.V. and
L.V. switchboards and complete automation of the plant. |
475 |
nov-90 |
gen-92 |
|
15 |
Customer |
Hydrowatt Abruzzo
S.p.A. (PE) |
|
|
|
|
|
Object: |
Realization
of Ponte Radio plant on Val di Foro Aqueduct:
Supply and mounting of one hydroelectric unit with 315 kW Francis turbines
completed with rapid automatic by-pass system, M.V. and L.V. switchboards and complete
automation of the plant. |
315 |
apr-92 |
mar-93 |
|
16 |
Customer |
Hydrowatt Abruzzo
S.p.A. (PE) |
|
|
|
|
|
Object: |
Realization
of Castellina plant on Val di Foro Aqueduct:
Supply and mounting of one hydroelectric unit with 450 kW Francis turbines
completed with rapid automatic by-pass system, M.V. and L.V. switchboards and complete
automation of the plant. |
450 |
apr-92 |
apr-93 |
|
17 |
Customer |
Italwatt s.r.l. (AP) |
|
|
|
|
|
Object: |
Replace
of turbine and modification of alternator of Amandola plant:
supply and mounting of 315 kW, 2500 lt/sec, 9,2 m
hydroelectric Kaplan unit with double regulation intubated propeller;
modification of existent generator. |
315 |
giu-98 |
lug-98 |
|
18 |
Customer |
Ente Irriguo Umbro
Toscano (AR) |
|
|
|
|
|
Object: |
Realization
of Montedoglio Dam plant on Tiber river:
Supply and mounting of two hydroelectric units with 600
kW Francis turbines, M.V. and L.V. switchboards and complete automation of
the plant. |
1.200 |
feb-99 |
dic-01 |
|
19 |
Customer |
Comune di Preci (PG) |
|
|
|
|
|
Object: |
Reactivation
of Piedivalle plant:
Supply and mounting of two hydroelectric units
with 220 kW Francis turbines, n.
2 automatic grille scrapers, M.V. and
L.V. switchboards and complete automation of the plant. |
440 |
ott-98 |
dic-03 |
|
20 |
Customer |
Azienda Speciale
dell'Acquedotto del Ruzzo (TE) |
|
|
|
|
|
Object: |
Supply
of source hydroelectric plant:
Supply and mounting of one automatic hydroelectric unit
with 12,5 kW Francis turbine. |
13 |
gen-97 |
giu-97 |
|
21 |
Customer |
Di Vincenzo Dino
& C. S.p.A. (CH) |
|
|
|
|
|
Object: |
Supply
of turbo-pump group:
Supply and mounting of one 700 kW Francis hydraulic
turbine for turbo-pump unit and control board. |
700 |
feb-98 |
mar-03 |
|
22 |
Customer |
Comune di Pacentro
(AQ) |
|
|
|
|
|
Object: |
Supply
of Municipal plant
Supply and mounting of one hydroelectric unit with 500
kW Pelton turbine, M.V. and L.V. switchboards and complete automation of the
plant. |
500 |
apr-99 |
feb-00 |
|
23 |
Customer |
Comune di Villa S.
Maria (CH) |
|
|
|
|
|
Object: |
Extension
of unit 1 of Castracane plant:
Supply and mounting of
automatic grille scraper extension of a Francis turbine with
replacement of 250 kW generator, modification
of M.V. and L.V. switchboards and automation of the plant. |
250 |
mag-00 |
nov-00 |
|
24 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Revamping
of Rovetino plant :
Supply and mounting of n. 2 hydroelectric units with
315 kW Francis turbines, completed with rapid by- pass automatic system,
supply and mounting of two 315 kW
Francis turbines completed with rapid automatic by-pass system, supply and
mounting of one hydro electric unit
with 132 kW Francis turbine completed with rapid automatic by-pass system,
L.V. switchboards and complete automation of the plant. |
762 |
dic-00 |
feb-02 |
|
25 |
Customer |
Comune di Bagni di
Lucca (LU) |
|
|
|
|
|
Object: |
Reactivation
of Ravacce plant :
Supply and mounting of one hyroelectric unit with a 630
kW Kaplan turbine, automatic grille scraper, n. 3 grids, M.V. and L.V. switchboards and automation of the plant. |
630 |
feb-01 |
set-02 |
|
26 |
Customer |
Hydrowatt S.p.A. (AP) |
|
|
|
|
|
Object: |
Realization
of Citeroni plant:
Supply and mounting of one hydroelectric unit with a 75
kW Francis turbine, completed with rapid automatic by-pass system, L.V.
switchboards and complete automation of the plant. |
75 |
mar-01 |
set-02 |
|
27 |
Customer |
Comune di Massa (MS) |
|
|
|
|
|
Object: |
Realizaztion
of Filanda di Forno plant:
Supply and mounting of 500 kW and 250 kW hydroelectric units with Francis
turbines, Medium Voltage and Low
Voltage switchboards and complete automation of the plant. |
750 |
mag-02 |
ago-04 |
|
28 |
Customer |
Ecowatt s.r.l. (PD) |
|
|
|
|
|
Object: |
Realization
of Ex Zecca plant:
Supply and mounting of one hyroelectric unit with a 630 kW Kaplan turbine,
automatic grille scraper, n. 3 grids, M.V. and L.V. switchboards and automation of the
plant. |
315 |
set-02 |
feb-03 |
|
29 |
Customer |
Italwatt s.r.l.
(AP) |
|
|
|
|
|
Object: |
Epansion
of Amandola plant:
Supply and mounting of one hyroelectric unit with a 65 kW Kaplan turbine,
L.V. switchboards and automation of
the plant. |
65 |
gen-03 |
ago-03 |
|
30 |
Customer |
Tonarelli S.p.A. (LU) |
|
|
|
|
|
Object: |
Realization
of Liegora plant:
Supply and mounting of 647 kW and 324 kW hydroelectric units with Pelton
turbines, automatic grille scraper, n. 3 grids, M.V. and L.V. switchboards and automation of the plant. |
971 |
mag-03 |
dic-05 |
|
31 |
Customer |
Comune di Comelico
Superiore (BL) |
|
|
|
|
|
Object: |
Realization
of Municipal plant on Rio Sasso acqueduct:
Supply and mounting of one 60 kW Pelton turbine, M.V.
and L.V. switchboards and complete automation of the plant. |
60 |
giu-04 |
set-05 |
|
32 |
Customer |
S.P.E.I. Societą
Produzione Energia Idroelettrica s.r.l. (PD) |
|
|
|
|
|
Object: |
Realization
of Molino Rubis plant:
Supply and mounting of one hyroelectric unit with a 394 kW Kaplan turbine. |
394 |
set-04 |
mar-06 |
|
33 |
Customer |
Le Trabe s.r.l.
(SA) |
|
|
|
|
|
Object: |
Realization
of Le Trabe plant:
Supply and mounting of one hyroelectric submarine unit with 124 kW Kaplan
turbine, L.V. switchboards and complete automation of the plant. |
124 |
feb-05 |
gen-06 |
|
34 |
Customer |
Comune di Pacentro
(AQ) |
|
|
|
|
|
Object: |
Generator
raplacement:
Supply and mounting of one 250 kW genertator hight efficency . |
|
mar-05 |
mag-05 |
|
35 |
Customer |
PEM Energia s.r.l.
(FC) |
|
|
|
|
|
Object: |
Realizazion
of Mulino plant:
Supply and mounting of one hyroelectric unit with a 114 kW Kaplan turbine,
automatic grille scraper, L.V.
switchboards and automation of the plant. |
110 |
lug-05 |
gen-07 |
|
36 |
Customer |
Ente Irriguo Umbro
Toscano (AR) |
|
|
|
|
|
Object: |
Realizaztion
Sovara plant:
Supply and mounting of one hydroelectric unit with 132 kW Francis turbines
completed with rapid automatic by-pass system, L.V. switchboards and complete automation
of the plant. |
132 |
ott-05 |
dic-06 |
|
37 |
Customer |
Consorzio Bonifica
Destra del Sele (SA) |
|
|
|
|
|
Object: |
Realization
of Castrullo plant:
Supply and mounting of one hydroelectric unit with 465 kW Pelton turbine,
M.V. and L.V. switchboards and complete automation of the plant. |
465 |
nov-05 |
lug-07 |
|
38 |
Customer |
Comune di Villa S.
Maria (CH) |
|
|
|
|
|
Object: |
Extension
of unit 2 of Castracane plant:
Extension of a Francis turbine with replacement of 250
kW generator, modification of M.V. and
L.V. switchboards and automation of the plant. |
250 |
mag-06 |
dic-06 |
|
39 |
Customer |
Megawatt s.r.l.
(PU) |
|
|
|
|
|
Object: |
Revamping
Ex Lanificio plant:
service turbines G1 and G2, supply and mounting of two genertators hight
efficency, M.V. and L.V. switchboards and complete automation of the plant. |
|
feb-06 |
set-06 |
|
40 |
Customer |
S.I.S. - Societą
Idroelettrica Settempedana s.r.l. (MC) |
|
|
|
|
|
Object: |
Realization
of Ponte S. Antonio plant:
Supply and mounting of one hyroelectric unit with a 412 kW Kaplan turbine,
automatic grille scraper, M.V. and L.V.
switchboards and automation of the plant. |
412 |
feb-05 |
mar-07 |
|
41 |
Customer |
Acciaierie Venete
S.p.A. (PD) |
|
|
|
|
|
Object: |
Revamping
Bellona 1° plant:
Supply and mounting of three 250 kW, 8000 lt/sec, 3,3 m hydroelectric
Kaplan unit with double regulation. |
666 |
set-06 |
lug-07 |
|
42 |
Customer |
Megawatt s.r.l. (PU) |
|
|
|
|
|
Object: |
Revamping
G3 Ex Lanificio plant:
service turbine G3, supply and mounting of one genertator hight efficency. |
|
giu-07 |
set-07 |
|
43 |
Customer |
Comune di Villa
Basilica (LU) |
|
|
|
|
|
Object: |
Realization
of Biecina plant:
Supply and mounting of one hydroelectric unit 400 kW Pelton turbine, M.V.
and L.V. switchboards and complete automation of the plant. |
400 |
feb-08 |
dic-08 |
|
44 |
Customer |
Comune di Tovo San
Giacomo (SV) |
|
|
|
|
|
Object: |
Revamping
Valmaremola plant:
Supply and mounting of one hydroelectric unit 132 kW Francis turbine, M.V.
and L.V. switchboards and complete automation of the plant and management of
the plant for 15 years. |
132 |
feb-08 |
dic-08 |
|
45 |
Customer |
SER Beef S.A.
(Argentina) |
|
|
|
|
|
Object: |
Realizzazione
centrale idroelettrica "Fausto Radici" in loc. Paso de Las Carretas
(AR):
Supply and mounting of three 408 kW, 3300 lt/sec, 14,5 m hydroelectric
Kaplan unit with double regulation, M.V. and L.V. switchboards and complete
automation of the plant. |
1.350 |
nov-08 |
mar-10 |
|
46 |
Customer |
Italwatt s.r.l. (AP) |
|
|
|
|
|
Object: |
Realization
of Uscerno plant:
Supply and mounting of one hyroelectric unit with a 355 kW Kaplan turbine
double regolation, automatic grille scraper, M.V. and L.V. switchboards and automation of the plant. |
355 |
mar-10 |
under
construction |
|
47 |
Customer |
Corema s.r.l. (LU) |
|
|
|
|
|
Object: |
Realization
of Uscerno plant:
Supply and mounting of two hyroelectric units with a 553 kW Pelton turbine,
M.V. and L.V. switchboards and
automation of the plant. |
1.106 |
apr-10 |
apr-11 |
|
48 |
Customer |
Consac Infrastrutture
S.p.A. (SA) |
|
|
|
|
|
Object: |
Realization
of micro hydroelectric units on Cilento Aqueduct:
Supply and mounting of eight micro and mini hydroelectric units with Pelton
e Francis turbines, L.V. switchboards
and automation of the plants. |
261 |
mag-10 |
under
construction |
|
49 |
Customer |
Idrogianico soc.
cons. a r.l. |
|
|
|
|
|
Object: |
Realization
of Gianico plant:
Supply and mounting of one hydroelectric unit 740 kW Pelton turbine, M.V.
and L.V. switchboards and complete automation of the plant and management of
the plant for 16 years. |
740 |
ago-10 |
under
construction |
|
49 |
Customer |
Comune di Norcia (PG) |
|
|
|
|
|
Object: |
Realization
of Benedettine plant :
Supply and mounting of one micro hydroelectric unit 1,75 kW, L.V.
switchboards and complete automation of the plant. |
2 |
nov-10 |
giu-11 |
|
49 |
Customer |
SAIM Miniere di Zolfo
(NA) |
|
|
|
|
|
Object: |
Realization
of Altavilla Irpinia Factory plant:
Supply and mounting of one hyroelectric unit with a 200 kW Kaplan turbine
double regolation, automatic grille scraper, M.V. and L.V. switchboards and automation of the plant. |
200 |
dic-10 |
under
construction |
|
|
|
|
|
|
|
|